1 m2 Pasangan Batu Merah Tebal 1 Bata, 1 Pc : 1 Ps | ||||||
BAHAN | | | | | | |
Batu Merah 5 x 11 x 22 cm | 140.000 | Bh | x Rp. | | = Rp. | - |
Semen Portland | 64.030 | Kg | x Rp. | | = Rp. | - |
Pasir Pasang | 0.059 | M3 | x Rp. | | = Rp. | - |
| | | Jumlah 1 | | = Rp. | - |
| | | | | | |
TENAGA | | | | | | |
Pekerja | 0.650 | OH | x Rp. | | = Rp. | - |
Tukang Batu | 0.200 | OH | x Rp. | | = Rp. | - |
Kepala Tukang | 0.020 | OH | x Rp. | | = Rp. | - |
Mandor | 0.030 | OH | x Rp. | | = Rp. | - |
| | | Jumlah 2 | | = Rp. | - |
| | | Jumlah (1) + (2) | | = Rp. | - |
| | | | | | |
1 m2 Pasangan Batu Merah Tebal 1 Bata, 1 Pc : 2 Ps | ||||||
BAHAN | | | | | | |
Batu Merah 5 x 11 x 22 cm | 140.000 | Bh | x Rp. | | = Rp. | - |
Semen Portland | 43.500 | Kg | x Rp. | | = Rp. | - |
Pasir Pasang | 0.080 | M3 | x Rp. | | = Rp. | - |
| | | Jumlah 1 | | = Rp. | - |
| | | | | | |
TENAGA | | | | | | |
Pekerja | 0.650 | OH | x Rp. | | = Rp. | - |
Tukang Batu | 0.200 | OH | x Rp. | | = Rp. | - |
Kepala Tukang | 0.020 | OH | x Rp. | | = Rp. | - |
Mandor | 0.030 | OH | x Rp. | | = Rp. | - |
| | | Jumlah 2 | | = Rp. | - |
| | | Jumlah (1) + (2) | | = Rp. | - |
| | | | | | |
1 m2 Pasangan Batu Merah Tebal 1 Bata, 1 Pc : 3 Ps | ||||||
BAHAN | | | | | | |
Batu Merah 5 x 11 x 22 cm | 140.000 | Bh | x Rp. | | = Rp. | - |
Semen Portland | 32.950 | Kg | x Rp. | | = Rp. | - |
Pasir Pasang | 0.091 | M3 | x Rp. | | = Rp. | - |
| | | Jumlah 1 | | = Rp. | - |
| | | | | | |
TENAGA | | | | | | |
Pekerja | 0.650 | OH | x Rp. | | = Rp. | - |
Tukang Batu | 0.200 | OH | x Rp. | | = Rp. | - |
Kepala Tukang | 0.020 | OH | x Rp. | | = Rp. | - |
Mandor | 0.030 | OH | x Rp. | | = Rp. | - |
| | | Jumlah 2 | | = Rp. | - |
| | | Jumlah (1) + (2) | | = Rp. | - |
| | | | | | |
1 m2 Pasangan Batu Merah Tebal 1 Bata, 1 Pc : 4 Ps | ||||||
BAHAN | | | | | | |
Batu Merah 5 x 11 x 22 cm | 140.000 | Bh | x Rp. | | = Rp. | - |
Semen Portland | 26.550 | Kg | x Rp. | | = Rp. | - |
Pasir Pasang | 0.093 | M3 | x Rp. | | = Rp. | - |
| | | Jumlah 1 | | = Rp. | - |
| | | | | | |
TENAGA | | | | | | |
Pekerja | 0.650 | OH | x Rp. | | = Rp. | - |
Tukang Batu | 0.200 | OH | x Rp. | | = Rp. | - |
Kepala Tukang | 0.020 | OH | x Rp. | | = Rp. | - |
Mandor | 0.030 | OH | x Rp. | | = Rp. | - |
| | | Jumlah 2 | | = Rp. | - |
| | | Jumlah (1) + (2) | | = Rp. | - |
| | | | | | |
| | | | | | |
| | | | | | |
1 m2 Pasangan Batu Merah Tebal 1 Bata, 1 Pc : 5 Ps | ||||||
BAHAN | | | | | | |
Batu Merah 5 x 11 x 22 cm | 140.000 | Bh | x Rp. | | = Rp. | - |
Semen Portland | 22.200 | Kg | x Rp. | | = Rp. | - |
Pasir Pasang | 0.102 | M3 | x Rp. | | = Rp. | - |
| | | Jumlah 1 | | = Rp. | - |
| | | | | | |
TENAGA | | | | | | |
Pekerja | 0.650 | OH | x Rp. | | = Rp. | - |
Tukang Batu | 0.200 | OH | x Rp. | | = Rp. | - |
Kepala Tukang | 0.020 | OH | x Rp. | | = Rp. | - |
Mandor | 0.030 | OH | x Rp. | | = Rp. | - |
| | | Jumlah 2 | | = Rp. | - |
| | | Jumlah (1) + (2) | | = Rp. | - |
| | | | | | |
1 m2 Pasangan Batu Merah Tebal 1 Bata, 1 Pc : 6 Ps | ||||||
BAHAN | | | | | | |
Batu Merah 5 x 11 x 22 cm | 140.000 | Bh | x Rp. | | = Rp. | - |
Semen Portland | 22.200 | Kg | x Rp. | | = Rp. | - |
Pasir Pasang | 0.102 | M3 | x Rp. | | = Rp. | - |
| | | Jumlah 1 | | = Rp. | - |
| | | | | | |
TENAGA | | | | | | |
Pekerja | 0.650 | OH | x Rp. | | = Rp. | - |
Tukang Batu | 0.200 | OH | x Rp. | | = Rp. | - |
Kepala Tukang | 0.020 | OH | x Rp. | | = Rp. | - |
Mandor | 0.030 | OH | x Rp. | | = Rp. | - |
| | | Jumlah 2 | | = Rp. | - |
| | | Jumlah (1) + (2) | | = Rp. | - |
| | | | | | |
1 m2 Pasangan Batu Merah Tebal 1 Bata, 1 Pc : 1 Kp : 10 Ps | ||||||
BAHAN | | | | | | |
Batu Merah 5 x 11 x 22 cm | 140.000 | Bh | x Rp. | | = Rp. | - |
Semen Portland | 10.080 | Kg | x Rp. | | = Rp. | - |
Pasir Pasang | 0.093 | M3 | x Rp. | | = Rp. | - |
Kapur Pasang | 0.028 | M3 | x Rp. | | = Rp. | - |
| | | Jumlah 1 | | = Rp. | - |
| | | | | | |
TENAGA | | | | | | |
Pekerja | 0.650 | OH | x Rp. | | = Rp. | - |
Tukang Batu | 0.200 | OH | x Rp. | | = Rp. | - |
Kepala Tukang | 0.020 | OH | x Rp. | | = Rp. | - |
Mandor | 0.030 | OH | x Rp. | | = Rp. | - |
| | | Jumlah 2 | | = Rp. | - |
| | | Jumlah (1) + (2) | | = Rp. | - |
| | | | | | |
1 m2 Pasangan Batu Merah Tebal 1/2 Bata, 1 Pc : 1 Ps | ||||||
BAHAN | | | | | | |
Batu Merah 5 x 11 x 22 cm | 70.000 | Bh | x Rp. | | = Rp. | - |
Semen Portland | 27.800 | Kg | x Rp. | | = Rp. | - |
Pasir Pasang | 0.028 | M3 | x Rp. | | = Rp. | - |
| | | Jumlah 1 | | = Rp. | - |
| | | | | | |
TENAGA | | | | | | |
Pekerja | 0.320 | OH | x Rp. | | = Rp. | - |
Tukang Batu | 0.100 | OH | x Rp. | | = Rp. | - |
Kepala Tukang | 0.010 | OH | x Rp. | | = Rp. | - |
Mandor | 0.015 | OH | x Rp. | | = Rp. | - |
| | | Jumlah 2 | | = Rp. | - |
| | | Jumlah (1) + (2) | | = Rp. | - |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
| | | | | | |
1 m2 Pasangan Batu Merah Tebal 1/2 Bata, 1 Pc : 2 Ps | ||||||
BAHAN | | | | | | |
Batu Merah 5 x 11 x 22 cm | 70.000 | Bh | x Rp. | | = Rp. | - |
Semen Portland | 18.950 | Kg | x Rp. | | = Rp. | - |
Pasir Pasang | 0.038 | M3 | x Rp. | | = Rp. | - |
| | | Jumlah 1 | | = Rp. | - |
| | | | | | |
TENAGA | | | | | | |
Pekerja | 0.320 | OH | x Rp. | | = Rp. | - |
Tukang Batu | 0.100 | OH | x Rp. | | = Rp. | - |
Kepala Tukang | 0.010 | OH | x Rp. | | = Rp. | - |
Mandor | 0.015 | OH | x Rp. | | = Rp. | - |
| | | Jumlah 2 | | = Rp. | - |
| | | Jumlah (1) + (2) | | = Rp. | - |