1 m2 | Plesteran 1 Pc : 8 Ps, Tebal 15 mm | |||||
BAHAN | | | | | | |
Semen Portland | | | 2.880 | Kg | x Rp. | |
Pasir Pasang | | | 0.024 | M3 | x Rp. | |
| | | | | Jumlah 1 | |
| | | | | | |
TENAGA | | | | | | |
Pekerja | | | 0.200 | OH | x Rp. | |
Tukang Batu | | | 0.150 | OH | x Rp. | |
Kepala Tukang | | | 0.015 | OH | x Rp. | |
Mandor | | | 0.010 | OH | x Rp. | |
| | | | | Jumlah 2 | |
| | | | | Jumlah (1) + (2) | |
| | | | | | |
1 m2 | Plesteran 1 Pc : 0,5 Kp : 3 Ps, Tebal 15 mm | |||||
BAHAN | | | | | | |
Semen Portland | | | 5.760 | Kg | x Rp. | |
Kapur Padam | | | 0.003 | M3 | x Rp. | |
Pasir Pasang | | | 0.013 | M3 | x Rp. | |
| | | | | Jumlah 1 | |
| | | | | | |
TENAGA | | | | | | |
Pekerja | | | 0.200 | OH | x Rp. | |
Tukang Batu | | | 0.150 | OH | x Rp. | |
Kepala Tukang | | | 0.015 | OH | x Rp. | |
Mandor | | | 0.010 | OH | x Rp. | |
| | | | | Jumlah 2 | |
| | | | | Jumlah (1) + (2) | |
| | | | | | |
1 m2 | Plesteran 1 Pc : 3 Kp : 10 Ps, Tebal 15 mm | |||||
BAHAN | | | | | | |
Semen Portland | | | 1.840 | Kg | x Rp. | |
Kapur Padam | | | 0.006 | M3 | x Rp. | |
Pasir Pasang | | | 0.014 | M3 | x Rp. | |
| | | | | Jumlah 1 | |
| | | | | | |
TENAGA | | | | | | |
Pekerja | | | 0.200 | OH | x Rp. | |
Tukang Batu | | | 0.150 | OH | x Rp. | |
Kepala Tukang | | | 0.015 | OH | x Rp. | |
Mandor | | | 0.010 | OH | x Rp. | |
| | | | | Jumlah 2 | |
| | | | | Jumlah (1) + (2) | |
| | | | | | |
1 m2 | Plesteran 0.5 Pc : 1 Kp : 4 Ps, Tebal 15 mm | |||||
BAHAN | | | | | | |
Semen Portland | | | 3.000 | Kg | x Rp. | |
Kapur Padam | | | 0.005 | M3 | x Rp. | |
Pasir Pasang | | | 0.019 | M3 | x Rp. | |
| | | | | Jumlah 1 | |
| | | | | | |
TENAGA | | | | | | |
Pekerja | | | 0.200 | OH | x Rp. | |
Tukang Batu | | | 0.150 | OH | x Rp. | |
Kepala Tukang | | | 0.015 | OH | x Rp. | |
Mandor | | | 0.010 | OH | x Rp. | |
| | | | | Jumlah 2 | |
| | | | | Jumlah (1) + (2) | |
| | | | | | |
1 m2 | Plesteran 1 Kp : 1 SM : 1 Ps, Tebal 15 mm | |||||
BAHAN | | | | | | |
Semen Merah | | | 0.009 | M3 | x Rp. | |
Kapur Padam | | | 0.009 | M3 | x Rp. | |
Pasir Pasang | | | 0.009 | M3 | x Rp. | |
| | | | | Jumlah 1 | |
| | | | | | |
TENAGA | | | | | | |
Pekerja | | | 0.200 | OH | x Rp. | |
Tukang Batu | | | 0.150 | OH | x Rp. | |
Kepala Tukang | | | 0.015 | OH | x Rp. | |
Mandor | | | 0.010 | OH | x Rp. | |
| | | | | Jumlah 2 | |
| | | | | Jumlah (1) + (2) | |
| | | | | | |
1 m2 | Plesteran 1 Kp : 1 SM : 2 Ps, Tebal 15 mm | |||||
BAHAN | | | | | | |
Semen Merah | | | 0.007 | M3 | x Rp. | |
Kapur Padam | | | 0.007 | M3 | x Rp. | |
Pasir Pasang | | | 0.015 | M3 | x Rp. | |
| | | | | Jumlah 1 | |
| | | | | | |
TENAGA | | | | | | |
Pekerja | | | 0.200 | OH | x Rp. | |
Tukang Batu | | | 0.150 | OH | x Rp. | |
Kepala Tukang | | | 0.015 | OH | x Rp. | |
Mandor | | | 0.010 | OH | x Rp. | |
| | | | | Jumlah 2 | |
| | | | | Jumlah (1) + (2) | |
0 komentar :
Posting Komentar